Grantees reported they received quotes for the camera project at the Southern Mississippi Institution (SMCI). A vendor has not been selected for the camera project at SMCI.
The team discussed updates on the data collection process. Staff are working on pulling numbers from the current investigations database to determine the database's ability to have a flag for those investigations involving PREA. The object is to be able to pull out those numbers for comparison purposes. Unsubstantiated allegation data is being gathered manually.
The coach discussed with PREA Coordinator's desire to have First Responder Cards made for the facility staff. The coach provided the PC with an example of First Responder pocket card and the grant manager with information on subsequent NCE request.
The coach provided the Commissioner with an update on grant progress. There was concern expressed that the camera installation goal may not be met by the grant deadline. The coach corresponded with the Deputy Commissioner about the need for expediency on meeting camera installation timeframe. The coach discussed the possibility of submitting an NCE; however, the grantee was encouraged spend the funds by the September 30, 2024 deadline.
The PC will attend the PREA Coordinators Working Group Conference on July 23-25, 2024.
Please check the box next to the following questions if the answer is 'yes'.
Please enter the applicable Event Date if there is an Event associated with this TTA.
When entering an Event Date, the Time is also required.
If the TTA is targeted to a particular audience or location, please complete the questions below.
Milestones are an element, activity, work product, or key task associated with completing the TTA (e.g. kick-off meeting, collect data from stake holders, deliver initial data analysis).
Please complete the fields below, if applicable, to create a milestone for this TTA.
Please respond to the Performance Metrics below. The Performance Metrics questions are based on the TTA Type indicated in the General Information section of the TTA.
Please submit a signed letter of support from your agency’s executive or other senior staff member. The letter can be emailed to or uploaded with this request. The letter should be submitted on official letterhead and include the following information:
- General information regarding the request for TTA services, i.e., the who, what, where, when, and why.
- The organizational and/or community needs specific to the request for TTA services.
- The benefits or anticipated outcomes from the receipt of TTA services.
By submitting this application to BJA NTTAC, I understand that upon approval of this application for TTA, the requestor agrees to keep BJA NTTAC informed of any circumstances that may impact the delivery of the TTA, including changes in the date of the event, event cancellation, or difficulties communicating with the assigned TTA provider.