Woodbury Pubic Safety (WPS) decided to push their remote site visit back from January to March 2021. In this reporting period, the action plan with the findings from the site visit were presented to WPS leadership. WPS decided to pause on moving forward with the CS360 implementation recommendations due to upcoming changes in leadership. In June 2021, WPS re-engaged with NPF and discussed CS360 implementation. NPF provided an Advisory Team workshop to an internal group from WPS. NPF plans to provide trainings in the next reporting period to WPS on understanding analysts for police manages, analysts 101, and communications.

TTA Short Name
Woodbury PS Support
Status of Deliverable
Type of Agency
Provider Reference
TTA Title
TTA Support for Woodbury Public Safety
TTA Point of Contact
TTAR Source
Deliverable Markup for Questions

Please check the box next to the following questions if the answer is 'yes'.

Is this TTA in support of implementing or maintaining an evidence-based or promising practice?
Yes
Is this TTA in response to emerging public safety needs?
Yes
Demographic - Gender
County
Arlington County
TTA Program Area
Program Area - Sub Topics
TTA Source
Demographic - Age
Demographic - Race
TTA Estimated Costs
Demographic - Ethnicity
Demographic - Other
BJA Grant Manager
Recipient Agency Scope
No
Event Date Markup

Please enter the applicable Event Date if there is an Event associated with this TTA.
When entering an Event Date, the Time is also required.

Display event on public TTA Catalog
No
Demographics Markup

If the TTA is targeted to a particular audience or location, please complete the questions below.

Milestones Markup

Milestones are an element, activity, work product, or key task associated with completing the TTA (e.g. kick-off meeting, collect data from stake holders, deliver initial data analysis).

Please complete the fields below, if applicable, to create a milestone for this TTA.

Milestone
Milestone Title
Introductory meeting
Milestone Description

The project team held an introductory call with WPD to discuss the agency's priorities and possible CS360 implementation.

Start Date
Actual Completion Date
Complete %
100
Milestone Title
Remote Site Visit
Milestone Description

NPF met with representatives from WPS and external community and governmental stakeholders over the course of two weeks. The groups included individuals from: WPS officers and leadership, WPS analyst, WPS internal communications team, Multicultural Advisory Committee, Woodbury school stakeholders, and the business community.

Start Date
Actual Completion Date
Complete %
100
Milestone Title
Action Plan
Milestone Description

The action plan was presented to WPS leadership following the remote site visit

Start Date
Actual Completion Date
Complete %
100
Milestone Title
Advisory Team Workshop
Milestone Description

The project team provided an Advisory Team workshop to an internal team from WPS to explain the role and responsibilities of the Advisory Team and the CS360 process

Start Date
Actual Completion Date
Complete %
100
Performance Metrics Markup

Please respond to the Performance Metrics below.  The Performance Metrics questions are based on the TTA Type indicated in the General Information section of the TTA.

Performance Metrics
Cover Letter Instructions

Please submit a signed letter of support from your agency’s executive or other senior staff member. The letter can be emailed to or uploaded with this request. The letter should be submitted on official letterhead and include the following information:

  1. General information regarding the request for TTA services, i.e., the who, what, where, when, and why.
  2. The organizational and/or community needs specific to the request for TTA services.
  3. The benefits or anticipated outcomes from the receipt of TTA services.

By submitting this application to BJA NTTAC, I understand that upon approval of this application for TTA, the requestor agrees to keep BJA NTTAC informed of any circumstances that may impact the delivery of the TTA, including changes in the date of the event, event cancellation, or difficulties communicating with the assigned TTA provider.

Please call [site:phone] if you need further assistance completing this application.

I Agree
Off
Archived
Off
Event Location Geo
POINT (-77.0519346 38.851214)
BJA Policy Advisor
BJA Policy Division
Remote TTAC ID
0